Summary
The bridge floods at 27-foot river stage and has gone underwater eight times in 15 years. The Commission picked the cheaper Build-Off alignment ($26-29M) and a mini roundabout at Elm Street, but construction money isn't secured — the city will pursue federal grants and any funding returns to the Commission.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 2, 2026.
Impact analysis
Design is covered by a $1.5 million federal grant; construction at $26-29 million still needs funding.
North Fargo commuters and hospital access — the bridge carries about 13,000 vehicles a day.